Operation of 3 crisis management bases in Tehran in the next 3 months
The new support and crisis management bases will soon be operational in the 7th, 12th and 18th districts of Tehran Municipality.
The new support and crisis management bases will soon be operational in the 7th, 12th and 18th districts of Tehran Municipality.
According to the report of Ambassador Arjan, Dr. Mohammad Alinejad, the Finance and Economic Deputy of Tehran Municipality along with Majid Amani, Managing Director of Engineering and Construction Organization of Tehran Municipality and Dr. Nasiri, Managing Director of Tehran City Crisis Prevention and Management Organization, attended the site of the crisis management base project in the 18th region and were closely informed about the progress of the crisis management support base project.
This project, with an infrastructure of 1,275 square meters on a land of 2,200 square meters and a physical progress of 84%, is under construction.
During this visit, Majid Amani, while presenting a report on the activities and planning carried out in order to complete and launch the bases, announced the possibility of operating 4 crisis management bases in the capital by the end of autumn.
Further, the financial and economic deputy of Tehran municipality issued orders to provide the financial resources needed for the projects, emphasizing the continuation of activities until the realization of the projects.
So far, 10 bases have been completed and put into operation, and currently the construction of 5 bases and the overhaul of 7 bases are in progress.
Based on the subsequent meeting of the visit and pre-opening coordination, it was decided that the new crisis management bases of districts 7 and 12 of the municipality will be put into operation within the next 3 months, at the same time as this base.
In another part of the meeting and based on the report of Nasiri, the CEO of the Crisis Prevention and Management Organization, decisions were made about the crisis management bases damaged in the Ramadan war to compensate for the damages and return this essential infrastructure of the city to the service cycle as soon as possible.